1 hr ago
Sion Railway Over Bridge Set To Open September 30
Mumbai’s Sion Railway Over Bridge is being rebuilt after the old bridge was found unsafe.
It was closed to traffic on August 1, 2024.
The closure made many commuters use longer and more crowded routes.
Workers have finished pouring concrete for the bridge’s main deck.
They are now completing safety barriers and the road surface.
A new pedestrian bridge is already open.
Nearby subway and approach-road work is also progressing.
Officials expect the rebuilt bridge to be completed by September 30, 2026.
Reconstruction of Mumbai’s Sion Railway Over Bridge is expected to be completed by September 30, 2026.
Central Railway has completed deck-slab concreting on both girders, while crash barriers and wearing coats are being installed.
The bridge was closed on August 1, 2024, after being declared unsafe, causing prolonged traffic disruption.
The BMC is rebuilding approach roads, with the LBS Marg subway and Sant Rohidas Marg subway now operational.
Project costs have increased from Rs 42.8 crore to nearly Rs 50 crore after steel-girder and approach-road works were added.
- Who
- Central Railway and the BMC are carrying out the reconstruction, with Mayor Ritu Tawde directing officials on finishing quality and greenery.
- What
- The Sion Railway Over Bridge and its approach roads are being reconstructed.
- Where
- The project is in Mumbai, including the Sion ROB and the LBS Marg–Sant Rohidas Marg approach in Dharavi.
- When
- The bridge was closed on August 1, 2024, and completion is expected by September 30, 2026.
- Why
- The old bridge was declared unsafe, and the reconstruction is part of MUTP-2 to support additional railway lines between CSMT and Kurla.
Key facts
- Expected completion
- September 30, 2026
- Closure date
- August 1, 2024
- Bridge age
- 112 years
- Current work
- Crash barriers and concrete wearing coats are being completed
- Nearby subway openings
- LBS Marg subway opened February 20, 2026; Sant Rohidas Marg subway opened July 14, 2026
- Project cost
- Increased from Rs 42.8 crore to nearly Rs 50 crore
- Railway purpose
- To facilitate Central Railway’s fifth and sixth additional lines between CSMT and Kurla
Quotes
Senior BMC Bridges Department official
A senior official in the Brihanmumbai Municipal Corporation Bridges Department
“Deck-slab concreting on both new girders is complete, while crash barriers and the concrete wearing coat are being completed. The new pedestrian bridge is also operational, and demolition of the remaining portion of the old bridge is complete.”
freepressjournal.in