Mumbai's Elphinstone Bridge Reopening Delayed Until Early 2027

Mumbai's Elphinstone Bridge Reopening Delayed Until Early 2027
Elphinstone bridge reopening hits hurdle, pushed to 2027 · indianexpress.com

Mumbai’s old Elphinstone bridge was replaced after it was removed a year ago.

The new bridge is taking longer than expected to build.

The railway section may be finished by November.

However, the full bridge may not open to cars and other traffic until January or February 2027.

Workers still need to place four large steel sections over the railway tracks.

This work needs at least 39 planned pauses in train operations over 25 days.

Rain and the festival season could make some railway pauses shorter.

MahaRail says it will keep working even if that happens.

The bridge is part of a larger connector project linking Elphinstone, Sewri and Worli.

Key facts

Original bridge age
112 years
Traffic opening target
January-February 2027
Railway portion target
November
Steel spans remaining
Four
Required railway blocks
At least 39
Duration of blocks
25 days
Project
Double-decker Elphinstone bridge-Sewri-Worli connector

Quotes

MahaRail official

An official from MahaRail, which is handling the railway portion of the bridge reconstruction.

“Even if for whatever reason, due to the rains or later trains due to the festival season, we get shorter railway blocks, we will continue the work so that there is some progress.”
indianexpress.com