Mumbai Sion Bridge Reconstruction Accelerated for September 2026 Completion

Mumbai Sion Bridge Reconstruction Accelerated for September 2026 Completion
Mumbai’s Sion Bridge work expedited: BMC targets September 30 completion, 5 months ahead of schedule · financialexpress.com

The Sion Bridge in Mumbai is being rebuilt.

Officials want the work finished by September 30, 2026, earlier than originally planned.

Central Railway is building the main bridge over the railway tracks.

The BMC is repairing the roads that lead to the bridge.

Two very heavy steel girders have been put into place.

Workers are now adding deck slabs to the bridge.

Two underground walkways have opened to help pedestrians cross more safely.

The finished project is expected to improve travel between Sion and Dharavi.

Key facts

Accelerated deadline
September 30, 2026
Original tender deadline
February 2027
Project framework
Mumbai Urban Transport Project (MUTP-2)
Bridge authority
Central Railway is handling the main bridge within railway limits.
Approach-road authority
The BMC Bridge Department is handling work within civic limits.
Steel girders
Both girders weigh 500 tonnes each; the second was launched on August 9, 2026.
Pedestrian facilities
Walkways opened on Lal Bahadur Shastri Road on February 20 and Sant Rohidas Road on July 14, 2026.
Remaining eastern approach work
The BMC said it can finish its portion in about 45 days after receiving possession of the site.