Politics · Indonesia · 1 day ago
Indonesia plans three egg and meat processing plants
Indonesia plans to build three plants to process eggs and meat into powder.
Agriculture Minister Andi Amran Sulaiman says the facilities would form part of a more connected livestock industry, from feed supplies to processing and sales.
The plants are intended to give farmers and livestock producers another outlet when egg and chicken production exceeds demand.
That could reduce reliance on selling fresh products, whose prices can fall when supply is high.
The government also hopes local production will replace imports of egg powder and reduce spending abroad.
Officials estimate an initial investment of about 200 billion rupiah per plant, potentially rising to 250 billion rupiah for a facility that processes meat.
The plans still need further study and cross-ministry approval, and construction could start in 2027 and take up to two years.
Indonesia plans to build three plants to process eggs and meat into flour products.
Agriculture Minister Andi Amran Sulaiman said construction could begin in 2027, subject to approval.
The government expects construction to take 1.5 years, with a maximum of two years.
The plants are intended to process surplus eggs and chicken meat and strengthen the livestock supply chain.
The government estimates initial investment at about Rp 200 billion per plant, potentially rising to Rp 250 billion for facilities that process meat.
- Who
- The Indonesian government, through the Ministry of Agriculture, plans the project. Agriculture Minister Andi Amran Sulaiman announced it.
- What
- It plans to build three plants to process eggs and meat into flour products.
- When
- Construction could start in 2027 if the plan is approved. It is expected to take 1.5 years, or up to two years.
- Where
- Indonesia. Specific plant locations are not stated.
- Why
- The plants are intended to strengthen the livestock industry, absorb surplus production and reduce reliance on imports of egg flour.
This story does not have two clearly opposing sides.
This is a permanent, fundamental solution. If the plants are built, we will stop importing egg flour.
We will propose this at the coordination meeting. Hopefully we can establish egg and meat flour plants.
Amran said the plan would be submitted for cross-ministry approval and that construction could start the following year if approved.
Amran said the government had agreed to build three plants and that feasibility studies would follow.
Construction is expected to begin, subject to approval.
- Planned facilities
- 3 plants
- Products
- Egg flour and meat flour
- Expected start
- 2027
- Construction period
- 1.5 years, up to 2 years
- Initial investment
- About Rp 200 billion per plant
- Possible investment for meat-processing facility
- Rp 250 billion