Sion ROB Reconstruction Milestone: 500-Tonne Girders Successfully Launched
Workers are building a new bridge in Mumbai called the Sion Road Over Bridge.
The old bridge was closed, so a new one is being built.
The hardest part was putting two giant steel beams, called girders, over the railway tracks below where trains still run.
Each girder weighs about 500 tonnes, which is heavier than many elephants.
The workers did this at night, when fewer trains run, to keep passengers safe.
They finished placing both giant girders in just two days.
The new bridge is wider than the old one so more railway lines can be added underneath.
The steel was made in Nagpur and put together near the site.
When it is finished, the bridge will help cars and buses cross between the Eastern Express Highway, LBS Road and Dharavi Road.
This work is part of a bigger project to make Mumbai's railway system better.
Central Railway completed the launching of both 500-tonne main girders of the reconstructed Sion Road Over Bridge within two days.
The second girder was launched during a specially planned three-hour night corridor block between Matunga and Kurla over the operational railway corridor.
Each girder weighs approximately 500 tonnes with an overall span of about 54.5 metres.
The reconstruction is part of the CSMT–Kurla 5th and 6th line project, one of Mumbai's major railway capacity enhancement projects.
The project has entered the next phase of deck slab construction, road approaches, road surfacing and crash barriers, and will restore connectivity between the Eastern Express Highway, LBS Road and Dharavi Road.
- Who
- Central Railway and the executing agency undertaking the reconstruction
- What
- Successful launching of the second 500-tonne girder, completing placement of both main girders of the new Sion ROB
- Where
- Sion, Mumbai, over the operational railway corridor between Matunga and Kurla
- When
- Within a period of two days, using two separate three-hour night corridor blocks
- Why
- To reconstruct the Sion ROB as part of the CSMT–Kurla 5th and 6th line project, accommodating additional railway lines and restoring vital east-west road connectivity
Key facts
- Project
- Reconstruction of Sion ROB under the CSMT–Kurla 5th and 6th line project
- Girder weight
- Approximately 500 tonnes each
- Girder span
- Approximately 54.5 metres
- Launch timeline
- Both girders launched within two days, in two three-hour night corridor blocks
- New vs old span
- New bridge span about 54.5 metres vs about 40 metres in the earlier structure
- Girder fabrication
- Fabricated at Nagpur, assembled at the site on the east-end approach
- Next phase
- Deck slab construction, road approaches, road surfacing, crash barriers and associated works
- Connectivity restored
- Between Eastern Express Highway, LBS Road and Dharavi Road