Sion ROB Reconstruction Milestone: 500-Tonne Girders Successfully Launched

Sion ROB Reconstruction Milestone: 500-Tonne Girders Successfully Launched
Sion ROB reconstruction work achieves major milestone with successful launch of 500 Tonne Girders in just 6 hours · freepressjournal.in

Workers are building a new bridge in Mumbai called the Sion Road Over Bridge.

The old bridge was closed, so a new one is being built.

The hardest part was putting two giant steel beams, called girders, over the railway tracks below where trains still run.

Each girder weighs about 500 tonnes, which is heavier than many elephants.

The workers did this at night, when fewer trains run, to keep passengers safe.

They finished placing both giant girders in just two days.

The new bridge is wider than the old one so more railway lines can be added underneath.

The steel was made in Nagpur and put together near the site.

When it is finished, the bridge will help cars and buses cross between the Eastern Express Highway, LBS Road and Dharavi Road.

This work is part of a bigger project to make Mumbai's railway system better.

Key facts

Project
Reconstruction of Sion ROB under the CSMT–Kurla 5th and 6th line project
Girder weight
Approximately 500 tonnes each
Girder span
Approximately 54.5 metres
Launch timeline
Both girders launched within two days, in two three-hour night corridor blocks
New vs old span
New bridge span about 54.5 metres vs about 40 metres in the earlier structure
Girder fabrication
Fabricated at Nagpur, assembled at the site on the east-end approach
Next phase
Deck slab construction, road approaches, road surfacing, crash barriers and associated works
Connectivity restored
Between Eastern Express Highway, LBS Road and Dharavi Road