Ayodhya Completes Namami Gange Projects to Improve Saryu Water

Ayodhya Completes Namami Gange Projects to Improve Saryu Water
Two Namami Gange projects boost sewage treatment in Ayodhya: NMCG · theprint.in

Ayodhya has finished two projects to help keep the Saryu river cleaner.

One project is a sewage treatment plant that can process 33 million litres of wastewater each day.

The other project collects wastewater from city drains and sends it for treatment.

This stops untreated sewage from flowing straight into the river.

The two projects cost Rs 260 crore.

The treatment plant was approved in 2021 and began operating in 2025.

Earlier drain-interception work was completed in 2021.

These projects are part of the larger Namami Gange effort to improve river health.

Key facts

Investment
Rs 260 crore for the two projects
Treatment capacity
33 million litres per day
Programme
Namami Gange Programme
Plant approval
Approved in 2021
Plant operation
Became operational in 2025
Drain network
Interception and diversion work completed in 2021
Earlier infrastructure
Ayodhya had an operational 12 MLD sewage treatment plant; a 2018 project targeted five drains carrying 5 MLD of sewage

Quotes

National Mission for Clean Ganga

Government mission implementing the Namami Gange river-cleaning programme

“Clean water, healthy city, and prosperous Ayodhya. This resolve has now become a reality.”
theprint.in
“Ayodhya is not just a city of faith; now it is also an example of clean water management”
theprint.in