Bina-Agasod Yard Work to Disrupt Over 40 Trains
Railway workers are rebuilding parts of two train stations in Madhya Pradesh.
The stations are Bina and Agasod.
The work will help connect them with a third railway line.
It is planned in stages from September 1 to October 15, 2026.
Because workers need safe space to build, many trains will be cancelled or changed.
Some trains will start or finish at a different station than usual.
Other trains will go around Bina station using a flyover.
The reports list 20 cancelled services and say more than 40 trains will be affected overall.
Passengers should check their train details before leaving.
Yard remodeling at Bina and Agasod stations will support a third railway line connecting them.
Pre-non-interlocking and non-interlocking work is scheduled in phases from September 1 to October 15, 2026.
Twenty listed train services, including MEMUs, expresses and intercity trains, will be cancelled during the work.
Several other services will start or end at alternate stations, including Khurai, Mungawali, Mahadevkhedi Junction and Malkhedi.
Passenger services are advised to check train routes, stoppages and station changes before travelling through Bina.
- Who
- Indian Railways, including West Central Railway and North Central Railway, is carrying out the work and changing services.
- What
- Yard remodeling and pre-non-interlocking and non-interlocking work will affect more than 40 train services, with 20 listed cancellations.
- Where
- At Bina station in Madhya Pradesh and Agasod station, with related changes on routes through Bina.
- When
- The work is scheduled in phases from September 1 to October 15, 2026; some affected return services continue through October 16.
- Why
- To connect Bina and Agasod with a third railway line and increase yard capacity, operational efficiency, reliability and punctuality.
Key facts
- Affected period
- Phased work from September 1 to October 15, 2026; some service changes run through October 16.
- Locations
- Bina station and Agasod station in Madhya Pradesh.
- Infrastructure project
- Yard remodeling to connect the two stations with a third railway line.
- Cancellations
- Twenty listed train services will be cancelled on specified dates between September 20 and October 16, 2026.
- Alternate stations
- Some trains will start or terminate at Khurai, Mahadevkhedi Junction, Mungawali, Bina Malkhedi Junction, Mandibamora, Santalpur or Malkhedi.
- Bypassed station
- Several passenger services, including Gwalior-Bina and Nagda-Bina services, will bypass Bina through a flyover.
- Passenger advice
- Travellers should verify train status, routes, stoppages and originating or destination stations before travelling.
- Reported name variation
- The reports identify Train 64618/64617's station as Lalitpur in one report and as “Santlptpur” in the other.