Indian Railways commissions Kavach 4.0 on 738 km
Indian Railways has started using a new safety system called Kavach 4.0 on two very busy train routes: Delhi-Mumbai and Delhi-Howrah.
This system helps trains avoid collisions.
It has been tested and is now working on 738 kilometers of tracks.
The system includes special cables, towers, and equipment on the tracks and trains.
More trains and tracks will get this safety system soon.
The government is also working on making trains safer for women by adding cameras and emergency buttons.
The system costs about Rs 50 lakh per kilometer for the tracks and Rs 80 lakh per train.
So far, Rs 2,354.36 crore has been spent on this project, with more money allocated for next year.
Over 40,000 people have been trained to use this new system.
Indian Railways has commissioned Kavach 4.0 on 738 Rkm of the Delhi-Mumbai and Delhi-Howrah corridors.
Kavach 4.0 is an upgraded version of the Automatic Train Protection (ATP) system, designed to prevent train collisions.
The system has been installed on the Palwal-Mathura-Nagda section (633 Rkm) and Howrah-Bardhaman section (105 Rkm).
Major improvements in Kavach 4.0 include increased location accuracy, better signal information in larger yards, and direct integration with electronic interlocking systems.
The system costs about Rs 50 lakh per kilometer for trackside installation and Rs 80 lakh per locomotive, with Rs 2,354.36 crore spent so far and Rs 1,673.19 crore allocated for 2025-26.
- Who
- Indian Railways
- What
- Commissioned Kavach 4.0 on 738 Rkm
- Where
- Delhi-Mumbai and Delhi-Howrah corridors
- When
- December 5, 2025 (Rajya Sabha update)
- Why
- To enhance safety and prevent train collisions
Key facts
- Kavach 4.0
- Upgraded version of Automatic Train Protection (ATP) system
- Routes Covered
- Delhi-Mumbai and Delhi-Howrah corridors
- Sections Commissioned
- Palwal-Mathura-Nagda (633 Rkm) and Howrah-Bardhaman (105 Rkm)
- Total Route km Commissioned
- 738 Rkm
- Optical Fibre Cable Laid
- 7,129 Km
- Telecom Towers Installed
- 860 nos
- Kavach at Stations
- 549 nos
- Track-side Equipment Installed
- 2,674 Rkm
- Kavach on Locos
- 4,154 nos
- Total Track-side Kavach Implementation
- 15,512 Rkm
- Locomotives to be Equipped
- 9,069 nos
- Cost per km (Trackside)
- Rs 50 lakh
- Cost per Locomotive
- Rs 80 lakh
- Total Expenditure (as of October 2025)
- Rs 2,354.36 crore
- Budget Allocation (2025-26)
- Rs 1,673.19 crore
- Technicians Trained
- 40,000+
- Loco Pilots Trained
- 30,000
Timeline
Bilaspur crash sparks safety alarm.
Railways responds, rolls out Kavach 4.0.
System now guards two major routes.
Quotes
Ashwini Vaishnaw
Railways Minister
“Following the success of Version 3.2 on 1,465 route km of South Central Railway, further refinements led to Version 4.0, which is now being rolled out across the remaining portions of the Delhi-Mumbai and Delhi-Howrah corridors.”
thehansindia.com
Sources
Railways commissions Kavach 4.0 on 738 Route km to boost safety on Delhi-Mumbai & Delhi-Howrah lines
RS: IndiGo issue raised; Kavach system, AI push dominate Question Hour
Kavach implementation taken up in Delhi–Mumbai, Delhi–Howrah corridors: Vaishnaw
Indian Railways commissions Kavach 4.0 on 738 route km across key corridors