Mahalaxmi Cable-Stayed Flyover Opening Delayed to December 2026

Mahalaxmi Cable-Stayed Flyover Opening Delayed to December 2026
Mumbai Infra Update: Mahalaxmi Cable-Stayed Flyover Opening Delayed To December 2026 Due To Utility-Shifting Work · freepressjournal.in

Mumbai is building a very special new bridge called a cable-stayed flyover.

It is the first bridge of its kind for Mumbai's civic body.

The bridge is being built near Mahalaxmi Railway Station.

It goes over the railway tracks and will connect two places called Saat Rasta and Mahalaxmi Ground.

A very tall steel column, called a pylon, is being built to hold up the bridge.

The pylon is about 78.5 metres high.

Part of the bridge is already finished, but another part is still waiting to be built.

The bridge was first supposed to be ready at the end of October.

But because workers had to move some underground pipes and wires, it will take about two extra months.

Now the bridge is expected to be ready by December 31, 2026.

Key facts

Location
Near Mahalaxmi Railway Station, along Keshavrao Khadye Marg, Mumbai
Bridge length
803 metres; 17.2 metres wide (23.01 metres within railway limits)
Pylon height
78.5 metres
Western span
95 metres (completed)
Eastern span
165 metres (pending, within railway premises)
Original opening date
October 31, 2026
Revised opening date
December 31, 2026
Connectivity
Connects Saat Rasta with Mahalaxmi Ground

Quotes

An official from the Bridge Department

Bridge Department official overseeing the flyover project

“"Although the construction work is progressing largely as scheduled, utility‑shifting work has caused a delay of around two months,"”
freepressjournal.in