PCMC Sets August Deadline as Railway Flyover Still Incomplete

PCMC Sets August Deadline as Railway Flyover Still Incomplete
This Key Shortcut Connecting Pimple Saudagar & Pimple Gurav To Old Mumbai-Pune Highway Has Been Closed For 3 Years - Why Is It Still Incomplete? · freepressjournal.in

People in a city called Pimpri-Chinchwad have been waiting a very long time for a new bridge called a flyover.

The bridge is being built over railway tracks so cars do not have to stop when a train passes.

It will give drivers a faster shortcut to an old highway.

The city government hired a construction company to build it, but the work took much longer than planned.

The builder was supposed to finish by March 2025, but only about 60 percent of the work was done in that time.

The city gave the builder three extra chances, and all three deadlines were missed.

Now the city says the builder must finish by the end of August or pay a fine of 1,000 rupees every day.

People who live nearby are unhappy because the road has been closed for years.

They now have to use roads that are very long or very crowded.

One resident even said the railway gate was fine and the flyover was not needed at all.

Key facts

Project
Railway flyover at Dairy Farm, Pimpri-Chinchwad
Length
1,290 metres
Width
17.20 metres
Approved cost
Rs 65.28 crore
Work order date
March 31, 2023
Original deadline
March 31, 2025 (about 60% work completed)
Extensions granted
3 (November 30, 2025; April 30, 2026; and a further three months)
Penalty
Rs 1,000 per day from September 1 if incomplete

Quotes

Vijay Bhojne

Executive engineer, Pimpri‑Chinchwad Municipal Corporation

“"This route needs to be started quickly because it is a shortcut for going from Pimple Gurav and Pimple Saudagar to Pimpri. Currently, there are two ways. One is via Nashik Phata and the old highway, which is far. The other is through Pimpri Camp, where there is heavy traffic because of the large number of vehicles and narrow roads. It has been over a couple of years since this road was closed."”
freepressjournal.in
“"Due to obstacles in the work, the contractor was given three extensions. The bridge work is in its final stages. Rain is limiting the execution of the work. If the contractor does not complete the work by the end of August, penalties will be imposed from 1st September. The price escalation of the contractor has been frozen."”
freepressjournal.in