1 week ago

Cabinet Approves Third, Fourth Rail Lines Between Gummidipoondi and Gudur

Cabinet Approves Third, Fourth Rail Lines Between Gummidipoondi and Gudur
Cabinet Clears Gummidipoondi-Gudur 3rd, 4th Rail Lines: Gurumoorthy · deccanchronicle.com

The Union Cabinet approved two more railway lines between Gummidipoondi and Gudur.

These lines will add space for more trains to travel.

The project will cover 90 kilometres.

It is expected to cost ₹2,229 crore and take four years to complete.

The extra tracks should help reduce train traffic and delays.

The work will include a large bridge over the Swarnamukhi River and many other bridges.

More railway capacity will also help move goods such as cement, containers and food grains.

Dr Maddila Gurumoorthy said the project could help businesses and the economies of Andhra Pradesh and Tamil Nadu.

Key facts

Project length
90 kilometres
Estimated cost
₹2,229 crore
Completion schedule
Four years
Major bridge
A 360-metre bridge across the Swarnamukhi River
Other structures
21 major bridges, 127 minor bridges and 34 road overbridges or road underbridges
Expected benefits
Greater passenger capacity, smoother train operations and improved freight handling
Freight commodities
Cement, containers, machinery, food grains, iron and steel