Bandra Fort connector adds ₹1,722 crore to VBSL project

Bandra Fort connector adds ₹1,722 crore to VBSL project
Bandra gets a ₹1,722-crore VBSL link to Fort — will it ease traffic? · indianexpress.com

The government approved a new road connector between the Versova-Bandra Sea Link and Bandra Fort.

It will cost about ₹1,722 crore.

The connector will be 3.55 kilometres long and have two lanes in each direction.

Officials hope it will make it easier for people in Bandra to reach the sea link.

This is because many roads inside Bandra are narrow and crowded.

Surveys of the ground are being done before construction begins.

Tenders may be invited in the next two to three months.

The connector could be finished around the same time as the sea link, which is targeted for May 2028.

The full sea-link project and its connectors are expected to cost ₹19,843 crore.

Key facts

Connector cost
₹1,722.40 crore
Connector length
3.55 kilometres
Road design
Two lanes in each direction, with a 1.269-km main carriageway, one loop and three ramps
Construction cost
₹1,183.79 crore
Total VBSL-related cost
₹19,843 crore, including the new connector
Tender timeline
Expected to begin within two to three months
Completion target
The Versova-Bandra Sea Link is targeted for May 2028

Quotes

Rajesh Patil

Vice-chairman and managing director of the Maharashtra State Road Development Corporation

“Currently, all roads leading to Pali Hill in Bandra (West) are (1+1) lanes”
indianexpress.com