3 hrs ago

Panel recommends clearance for Arunachal’s Upper Subansiri project

Panel recommends clearance for Arunachal’s Upper Subansiri project
Arunachal’s Upper Subansiri project gets green nod recommendation, 1.35 lakh trees at risk · indianexpress.com

An expert group has recommended allowing a large dam project in Arunachal Pradesh.

The project would produce electricity and help control floods.

It would include a 237-metre-high dam on the Subansiri River.

Building it would require using forest land and cutting about 1.35 lakh trees.

The project still needs an important forest clearance before it can receive final environmental approval.

New forests are proposed on degraded land in Madhya Pradesh to compensate for the forest diversion.

The expert group warned that cutting trees could harm animals, habitats and biodiversity.

It asked the project developer to reduce tree loss and restore damaged areas.

The project could also affect households and other hydropower projects downstream.

Key facts

Project capacity
1,605 MW
Forest diversion
2,733 hectares in Arunachal Pradesh
Trees at risk
Approximately 1.35 lakh trees
Proposed dam
237 metres high
Reservoir size
22.2 square kilometres at full reservoir level, with a length of about 50 kilometres
Compensatory afforestation
5,466 hectares of degraded forest land at 144 sites in Madhya Pradesh
Potentially affected households
1,139 households

Quotes

Supreme Court of India

The court whose 2009 directive was noted during appraisal of the upstream project.

“any proposal on the upper stream of the Subansiri River would be considered independently on its own merit by the standing committee as and when submitted by the proponents.”