Congress Challenges Centre’s Block on New Ganderbal Hydropower Project

Congress Challenges Centre’s Block on New Ganderbal Hydropower Project
Congress Slams ‘Institutional Affront’ As Centre Blocks Clearance for J&K Power Project · deccanchronicle.com

A power project called New Ganderbal is planned in Jammu and Kashmir.

It would make 93 megawatts of electricity.

A central environment committee refused to give the project more time under its existing environmental approval.

The committee said no construction has started, even though the project has been planned for many years.

It also said the work and environmental protections would not finish by 2028.

Congress leaders said the elected Jammu and Kashmir government should have been consulted.

They called the decision an insult to democratic institutions.

The project has faced cancelled contracts, new tenders, and rising costs.

If completed, it is expected to produce much more electricity for Kashmir and replace an older power station.

Key facts

Project capacity
93 megawatts
Project location
Nallah Sindh, Ganderbal district, Jammu and Kashmir
Original environmental clearance
Granted in September 2013
Requested extension
Two years, through September 26, 2028
Estimated annual generation
382.82 GWh
Cost increase
From ₹965.87 crore in 2014 to ₹1,610.55 crore in 2021
Planned replacement
The ageing 15-megawatt Ganderbal hydropower station

Quotes

Nizamuddin Bhat

Congress MLA in the Jammu and Kashmir Legislative Assembly

“This is nothing short of an institutional affront—proof that crucial decisions are now being taken over the heads of the elected government, in complete disregard of the democratic mandate it carries.”
deccanchronicle.com
“The decision was taken without consulting the Chief Minister and other concerned ministries.”
deccanchronicle.com

MoEFCC Expert Appraisal Committee

Environmental appraisal committee reviewing the New Ganderbal project

“Even if a further extension of two years up to 26.09.2028 is considered, the project construction works as well as implementation of the EMP would still not be completed within the extended validity period.”