Godavari Drinking Water Project Accelerated for October 2027 Completion

Godavari Drinking Water Project Accelerated for October 2027 Completion
Wrap up Godavari drinking water project by Oct 2027: Hyderabad Metro MD · thehansindia.com

A large project is being built to bring more drinking water to Hyderabad.

The water will come from the Godavari through Mallannasagar.

Officials want the project finished by October 2027.

It is expected to cost ₹7,360 crore.

Most of the water will be used for people in Hyderabad.

Some water will help rejuvenate Osmansagar, Himayatsagar and the Musi.

Workers are building a treatment plant, a storage reservoir and pipelines.

Officials told construction companies to use more workers and machines so different parts can be built at the same time.

They also checked a pipeline test to make sure it can handle pressure without leaking.

Key facts

Estimated cost
₹7,360 crore
Completion target
October 2027
Water transfer
20 TMC of Godavari water from Mallannasagar to Hyderabad
Water allocation
17.50 TMC for Hyderabad’s drinking water needs and 2.50 TMC for rejuvenation works
Treatment plant
A 1,170 MLD water treatment plant under construction at Ghanpur
Master balancing reservoir
An 80-million-litre reservoir under construction
Pipeline progress
About 10 km completed under Packages 1 and 2
Pipeline testing
Hydraulic testing was conducted on a 984-metre pipeline section