Hungary’s Paks Nuclear Plant Nears Full Capacity by Wednesday

Hungary’s Paks Nuclear Plant Nears Full Capacity by Wednesday
Hungary Paks nuclear plant could operate at full capacity by Wednesday, PM Magyar says · theprint.in

Hungary’s Paks nuclear plant had to reduce its electricity production because the Danube River became unusually low.

The river provides water used to cool the plant.

The plant was producing only a little more than one-tenth of its normal output earlier this month.

Water levels have since risen, and workers have carried out engineering work near the plant.

The plant restarted its third reactor late Saturday.

Four of its eight turbines were producing electricity on Sunday.

Officials say the plant could return to full production by Wednesday.

Temporary barges and a new riverbed sill helped keep enough water available while longer-term work continued.

Key facts

Plant capacity
2 gigawatts, or 2,000 megawatts
Current output
About 800 megawatts, based on operator data
Expected full restart
By Wednesday
Electricity share
Nearly half of Hungary’s electricity
Reactor status
Reactor 3 restarted late Saturday
Turbines operating
Four of eight turbines were producing electricity on Sunday
Temporary measures
Two barges were sunk near Paks to help maintain water levels
River project
Hungary began constructing a riverbed sill to regulate water flow

Quotes

Peter Magyar

Hungary’s prime minister

“Four turbines out of eight are producing electricity already at Paks. Full restart is underway, the nuclear plant could be producing 2,000 megawatts again by Wednesday”