1 week ago
Hungary’s Paks Nuclear Plant Nears Full Capacity by Wednesday
Hungary’s Paks nuclear plant had to reduce its electricity production because the Danube River became unusually low.
The river provides water used to cool the plant.
The plant was producing only a little more than one-tenth of its normal output earlier this month.
Water levels have since risen, and workers have carried out engineering work near the plant.
The plant restarted its third reactor late Saturday.
Four of its eight turbines were producing electricity on Sunday.
Officials say the plant could return to full production by Wednesday.
Temporary barges and a new riverbed sill helped keep enough water available while longer-term work continued.
Paks restarted reactor 3 late Saturday, according to Prime Minister Peter Magyar.
Four of the plant’s eight turbines were producing electricity on Sunday.
The plant currently generates about 800 megawatts, based on operator data.
Rising Danube water levels and river engineering work helped prevent a full shutdown.
The 2-gigawatt facility could return to full output by Wednesday, producing nearly half of Hungary’s electricity.
- Who
- Hungary’s Paks nuclear plant and Prime Minister Peter Magyar.
- What
- The plant is restarting after cutting output because of low Danube water levels and could regain full capacity.
- Where
- At the Paks nuclear plant on the Danube in Hungary.
- When
- Reactor 3 restarted late Saturday; Magyar announced the expected Wednesday full-capacity target on Sunday.
- Why
- Rising river levels and engineering measures improved the plant’s access to cooling water after drought caused record-low Danube levels.
Key facts
- Plant capacity
- 2 gigawatts, or 2,000 megawatts
- Current output
- About 800 megawatts, based on operator data
- Expected full restart
- By Wednesday
- Electricity share
- Nearly half of Hungary’s electricity
- Reactor status
- Reactor 3 restarted late Saturday
- Turbines operating
- Four of eight turbines were producing electricity on Sunday
- Temporary measures
- Two barges were sunk near Paks to help maintain water levels
- River project
- Hungary began constructing a riverbed sill to regulate water flow
Quotes
Peter Magyar
Hungary’s prime minister
“Four turbines out of eight are producing electricity already at Paks. Full restart is underway, the nuclear plant could be producing 2,000 megawatts again by Wednesday”