Work is continuing at Mumbai’s CSMT railway station.

The railway has extended a traffic and electricity block until September 5, 2026.

This means some trains will not reach CSMT and will instead stop at Dadar or Thane.

The work is part of the station’s redevelopment.

Railway officials have asked passengers to plan their journeys carefully.

Separately, workers upgraded a complicated track arrangement at Pune Yard.

They replaced several rails and other track equipment with stronger components.

Railway officials expect this to make the yard more reliable and ready for heavier train traffic.

Key facts

CSMT block extension
Traffic and power restrictions continue until September 5, 2026.
Affected CSMT platforms
Platforms 16 and 17 are involved in the redevelopment work.
Short-terminated at Dadar
Train Nos. 12810, 12112 and 22120 will continue to terminate at Dadar.
Short-terminated at Thane
Train No. 12134 Mangaluru-CSMT Express will continue to terminate at Thane.
Pune track upgrade
The fourth 52 kg Diamond Double Slip, Nos. 251/252, was converted to a 60 kg configuration.
Pune work duration
The conversion was completed during a nine-hour block on August 23, from 8 a.m. to 5 p.m.
Workforce
The Pune project involved 200 permanent-way labourers, 25 signalling and telecommunications staff, five P-Way supervisors and eight S&T supervisors, among others.