2 weeks ago
Mumbai Coastal Road North Link Targets December 2028 Completion
Mumbai is building a new coastal road connection between Versova and Bhayandar.
The final section is called the Dahisar-Bhayandar Link Road.
Workers have started building the foundations for its bridges.
A special construction yard in Bhayandar is making large concrete parts.
Officials say 60 piles, five pile caps, four piers, pier caps and nine bridge segments are complete.
More bridge-building equipment is expected to start work in October.
The civic body wants the link finished by December 2028.
The whole project could reduce the journey from 90–120 minutes to about 15–20 minutes.
Piling and pile-cap work has begun for the Dahisar-Bhayandar Link Road bridge foundations.
Launching-girder work is scheduled to begin in the second week of October.
A Bhayandar casting yard is producing precast components for the project.
The 5.135-kilometre link includes elevated roads, creek structures, interchanges and flyovers.
The wider project is expected to cut Versova-Bhayandar travel time to 15–20 minutes.
- Who
- The Brihanmumbai Municipal Corporation, its Bridge department and project officials, including Additional Municipal Commissioner Abhijit Bangar.
- What
- Construction of the Dahisar-Bhayandar Link Road, the final section of Mumbai’s Coastal Road (North) project, is advancing.
- Where
- The project connects Versova and Bhayandar, with construction activity including a casting yard in Bhayandar.
- When
- Piling and pile-cap work is underway; launching-girder work is planned for the second week of October, with completion targeted for December 2028.
- Why
- The project is intended to improve the coastal connection and reduce travel time between Versova and Bhayandar.
Key facts
- Overall project length
- Around 60 kilometres, including interchanges and connector roads
- DBLR length
- Approximately 5.135 kilometres
- Main elevated road
- 3.83 kilometres long and 45 metres wide
- Estimated cost
- Rs. 20,000 crore
- Construction completed
- 60 piles, five pile caps, four piers, pier caps and nine bridge segments
- Target completion
- December 2028
- Expected travel time
- 15–20 minutes between Versova and Bhayandar, compared with 90–120 minutes
Quotes
BMC Bridge department official
An unnamed official from the Brihanmumbai Municipal Corporation’s Bridge department
“So far, 60 piles, five pile caps, four piers, pier caps and nine bridge segments have been completed. The site is equipped with advanced construction machinery, with a temporary access bridge already operational”