Thane Connectivity Projects Advance as Creek Bridge Piling Exceeds 95%

Thane Connectivity Projects Advance as Creek Bridge Piling Exceeds 95%
Thane connectivity boost: Creek bridge, coastal road and elevated highway projects gather pace · financialexpress.com

Several big road projects are being built in and around Thane.

The Gaimukh–Payegaon Creek Bridge is 6.5 kilometres long.

Workers have finished more than 95% of its piling work, but the whole project is about 25% complete.

The bridge will connect Gaimukh with Chinchoti and Payegaon.

It should give cars and trucks a more direct way to reach Bhiwandi and Vasai.

Another project is a six-lane coastal road between Balkum and Gaimukh.

A separate elevated road will run between Anand Nagar and Saket.

Together, these projects are intended to provide more routes and reduce traffic on busy roads.

Key facts

Creek bridge length
6.5 kilometres
Creek bridge piling
More than 95% complete
Overall bridge completion
Around 25%
Bridge connection
Gaimukh on Ghodbunder Road to Chinchoti and Payegaon
Thane Coastal Road
13.45 kilometres and six lanes, between Balkum and Gaimukh
Anand Nagar–Saket elevated road
8.24 kilometres and six lanes, along the Eastern Express Highway
Connected infrastructure
Mumbai–Ahmedabad High-Speed Rail corridor, Virar–Alibaug Multimodal Corridor, Diva–Vasai railway line, National Highway 48 and Anjur–Chinchoti Road