BMC Moves to Drop Two Contractors Over Delayed Road Work

BMC Moves to Drop Two Contractors Over Delayed Road Work
275 roads, Rs 380 crore work pending as BMC moves to drop two contractors · indianexpress.com

Mumbai’s civic body wants to build concrete roads instead of asphalt roads.

It says two contractors are moving too slowly on the project.

Work has not started on 275 roads.

The unfinished work is estimated to cost Rs 380 crore.

The BMC says the contractors may not finish by March 2027.

It plans to stop the unfinished parts of their contracts and invite new bids.

The contractors say they face problems such as short work hours in busy areas and the rainy season.

One contractor also says it has already completed 154 of its 182 assigned roads.

Key facts

Roads awaiting work
275 roads
Estimated pending work
Rs 380 crore
Overall project
2,175 roads covering 712 km
Total contracts awarded
Rs 17,700 crore
Completion deadline
March 2027
Proposed next step
Fresh tender likely to be floated early next year
Contractors involved
NCC Limited and Eagle Infra India Limited

Quotes

Eagle Infra spokesperson

Spokesperson for Eagle Infra India Limited, one of the contractors working on the BMC project.

“In south Mumbai, especially in areas like Marine Drive, Churchgate, Colaba and Malabar hill there is a logistical issue. Being a VIP area the roads cannot be closed for a maximum of four hours, therefore we get a very short window for completing the work.”
indianexpress.com
“We were given 182 roads for concretisation. These roads were located in areas like Mankhurd, Chembur, Ghatkopar and Mulund in the eastern suburbs. We have completed work in 154 of them and have handed them over to the civic body.”
indianexpress.com