Thane Coastal Road Reaches 40% Progress, Piling Work Nears Completion

Thane Coastal Road Reaches 40% Progress, Piling Work Nears Completion
Thane Coastal Road-1 Achieves 40% Progress In 14 Months With 77% Piling Work Completed Along 13.45-Km Corridor · freepressjournal.in

The Thane Coastal Road-1 is a new six-lane road being built near Thane.

Construction has reached 40% completion after 14 months.

Workers have finished most of the foundation piles needed for the road.

They have also built many piers and installed hundreds of large bridge beams called girders.

Parts of the road will be elevated to reduce harm to mangrove areas.

The route will connect Kharegaon with Gaymukh.

It is intended to make travel and freight movement easier while reducing traffic on Ghodbunder Road.

Later, it is planned to connect with a tunnel toward Bhayandar.

Key facts

Overall progress
40% after 14 months
Corridor length
13.45 kilometres
Working piles
332 of 426 completed, or 77%
Piers
277 completed, or 65%
I-girders
501 of 1,632 installed, or about 30%
Elevated section
8.11 kilometres through the mangrove belt
Creek bridge
240 metres