Bhopal Metro Tunnel Nears Completion, Phase Two Targets 2028

Bhopal Metro Tunnel Nears Completion, Phase Two Targets 2028
Bhopal Metro’s First Underground Tunnel Nears Completion, Entire Phase-2 Targeted For 2028 · freepressjournal.in

Bhopal is building an underground tunnel for its metro train.

The first tunnel is 500 metres long, and about 350 metres of it has been dug.

A second digging machine has also moved forward on the same stretch.

The work took longer than first planned because of technical problems, pauses and the ground conditions.

Metro officials say the remaining tunnelling should finish by November.

Work at Shahi Kabristan paused after a local representative raised concerns about the cemetery.

Officials promised to keep construction in an open area and avoid affecting any graves.

The whole Phase-2 metro corridor is expected to be ready by the end of 2028.

Key facts

Tunnel section
Railway Station–Pul Patra; 500 metres
Progress
One TBM has advanced about 350 metres; the other about 300 metres
Expected tunnelling completion
November
Phase-2 corridor
16.74-kilometre Orange Line from Subhash Nagar to Karond
Overall target
End of 2028
Additional proposed underground section
3.39 kilometres between Pul Patra and Sindhi Colony
Shahi Kabristan agreement
Work to stay in an open portion; officials said no grave would be affected