Chennai Metro Phase II Records Three TBM Breakthroughs

Chennai Metro Phase II Records Three TBM Breakthroughs
Chennai Metro Phase II project achieves 3 tunnel boring machine breakthroughs in 3 days - Infrastructure News · financialexpress.com

Chennai Metro is building underground train tunnels in several parts of the city.

Three large tunnel-making machines reached stations on three days in a row.

Kaveri reached Kilpauk Medical College station.

Maruthan reached Villivakkam station.

Adyar reached RK Salai station after digging a 915-metre tunnel.

Adyar had to pass under or near important buildings and roads.

Chennai Metro Rail Limited said the work caused no major ground settlement or damage to existing infrastructure.

The three breakthroughs are being treated as an important step in building Phase II.

Key facts

Breakthroughs
Three TBMs reached stations on three consecutive days.
TBM locations
Kaveri reached Kilpauk Medical College, Maruthan reached Villivakkam and Adyar reached RK Salai.
Adyar tunnel length
915 metres between Royapettah and RK Salai stations.
Construction conditions
The tunnel passed through silty sand with approximately 9 to 13 metres of overburden.
Cutterhead interventions
CMRL reported 11 cutterhead interventions during Adyar’s drive.
Project section
The work is part of Corridor 3’s 12-kilometre underground section between Kellys and Taramani.
TBMs under TU02
The Adyar breakthrough was described as the 10th TBM breakthrough under the TU02 contract.

Quotes

Chennai Metro Rail Limited

The public agency responsible for Chennai Metro operations and project implementation

“Kaveri, Marutham and Adyar have officially arrived at their respective stations to keep tunnelling on track.”
financialexpress.com
“without any major ground settlement or adverse impact on existing infrastructure.”
financialexpress.com