Major Geological Hurdle Cleared as SLBC Tunnel Construction Advances

Major Geological Hurdle Cleared as SLBC Tunnel Construction Advances
Major geological hurdle cleared at SLBC tunnel · thehansindia.com

Workers building the Srisailam Left Bank Canal tunnel have passed through a difficult area of unstable rock.

Officials say they excavated about 700 metres in five to six months.

The main tunnel is 43.968 kilometres long and is about 79% complete.

Workers are using equipment and safety measures to keep excavation moving.

The work currently advances about seven to eight metres each day.

Officials hope to make each construction cycle shorter.

The tunnel is planned to carry more than 30 TMC of water to upland areas.

The minister said Tunnel 1 could break through in May or June 2028, while lining work has restarted on Tunnel 2.

Key facts

Main tunnel length
43.968 km
Main tunnel progress
Approximately 79% complete, with 9.1 km remaining
Recent excavation
About 700 metres over five to six months: 450 metres from the outlet and 250 metres from the inlet
Current excavation rate
An average of seven to eight metres daily
Construction cycle
Reduced from 48 hours to 20–24 hours; officials expect it to reach 10 hours from late October or early November
Tunnel 1 projected breakthrough
May–June 2028
Tunnel 2
7.1 km long; lining work has resumed after a prolonged interruption