Hyderabad Commission Orders Realty Firm to Pay ₹55.8 Lakh
Suresh Kumar Chinta put ₹17.5 lakh into a white sandalwood plantation plan.
The land was registered in his name, and an agreement said the company would plant and care for the trees.
The company also promised him regular payments.
It stopped making those payments in October 2023.
Chinta asked a consumer commission to help him.
The company did not appear when the case was heard.
The commission said the agreement was still valid and the company had not followed it.
It ordered the company to pay ₹60,000 each month for 93 months.
The total ordered under that part was ₹55.8 lakh, along with ₹25,000 for mental agony and ₹5,000 in legal costs.
Suresh Kumar Chinta invested ₹17.5 lakh with Square and Yards Infra Pvt. Ltd. in 2023.
The agreement involved agricultural land registered in Chinta’s name for growing white sandalwood trees.
The company promised monthly payments but stopped paying in October 2023, according to the report.
The Hyderabad consumer commission heard the case ex parte after the company and other parties failed to appear.
The commission ordered ₹60,000 monthly payments from 10 October 2023 to 10 June 2031, totaling ₹55.8 lakh, plus compensation and legal costs.
- Who
- Suresh Kumar Chinta and Gurgaon-based real estate firm Square and Yards Infra Pvt. Ltd.
- What
- The Hyderabad consumer commission ordered the company to make lease payments totaling ₹55.8 lakh, plus compensation and legal costs.
- Where
- The case was decided by the Hyderabad consumer commission; the company is based in Gurgaon.
- When
- The investment and land registration occurred in 2023; payments were ordered for 10 October 2023 through 10 June 2031.
- Why
- The commission found that the company failed to honor a valid lease agreement requiring payments connected to a white sandalwood plantation investment.
Key facts
- Investor
- Suresh Kumar Chinta
- Company
- Square and Yards Infra Pvt. Ltd.
- Initial investment
- ₹17.5 lakh
- Ordered monthly payment
- ₹60,000
- Payment period
- 10 October 2023 to 10 June 2031
- Total ordered lease payments
- ₹55.8 lakh over 93 monthly payments
- Additional awards
- ₹25,000 for mental agony and ₹5,000 for legal costs