Kolkata Pink Line Wins Clearance After Years of Delays

Kolkata Pink Line Wins Clearance After Years of Delays
Kolkata Metro’s Pink Line from Baranagar to Barrackpore gets civic clearance · indianexpress.com

Kolkata wants to build a Metro Pink Line between Baranagar and Barrackpore.

The line will run above the busy B T Road.

Construction was delayed because large water pipes are underneath the road.

The Kolkata Municipal Corporation has now allowed one old 48-inch pipe to be closed.

It also approved building a new 72-inch pipe for water supply.

Rail Vikas Nigam Limited is seeking a contractor to build the viaduct and 10 stations.

People hope the metro will make trips to Kolkata faster and more comfortable.

They also hope better transport will bring more businesses and industries to the area.

Key facts

Metro corridor
Baranagar to Barrackpore Pink Line
Reported length
12.40 kilometres in one report; 12.5 kilometres in another
Planned stations
10
Pipeline obstacle
A legacy 48-inch water transmission or drinking-water pipeline beneath B T Road
Replacement pipeline
A new 72-inch pipeline from the Indira Gandhi Water Treatment Plant in Palta to the Talla Pumping Station
Construction agency
Rail Vikas Nigam Limited
Estimated contract value
Nearly Rs 1,587.39 crore
Bid deadline
September 29, 2026

Quotes

Biplab Mukherjee

A resident of Agarpara

“The ball is in the Metro Railway’s court now. We wish to see timely completion of this project.”
thehansindia.com
“We have been waiting for over 10 years now. However, no progress has been made till now.”
thehansindia.com

Sagnik Majumdar

A resident of Barrackpore

“The new government has promised a lot. It should concentrate on more industries in this area, now that it is getting connected to the city.”
thehansindia.com