Mumbai Road Concretisation To Resume October 1, Finish May 2027

Mumbai Road Concretisation To Resume October 1, Finish May 2027
Mumbai Road Concretisation To Resume From October 1; BMC Targets Completion Of All Roads By May 2027 · freepressjournal.in

Mumbai plans to restart work on its roads on October 1.

The work was paused before the monsoon season.

Workers will first finish roads that are already partly completed.

Other roads will start after traffic officials give permission.

The project aims to make roads less prone to potholes.

It covers thousands of roads across the city.

The first phase should finish by December 2026.

The entire project is expected to finish by May 2027.

Key facts

Project cost
₹17,700 crore
Roads covered
2,179 roads
Total length
715 kilometers
Work restart
October 1, after the monsoon break
Current status
1,589 roads completed; 316 partially completed; 274 not started
Deadlines
Phase 1 by December 2026; all work by May 2027
Reported progress
The article says 81% is completed, 10% is partially completed, and 9% has not started; it also gives the separate road counts above.

Quotes

Senior BMC Roads department officer

A senior official in the BMC Roads department

“We will begin with the partially completed roads, and simultaneously apply for Traffic police NOC to start work on new roads.”