MCD Commissioner Flags Delays in CAQM Road Works Before Pollution Season

MCD Commissioner Flags Delays in CAQM Road Works Before Pollution Season
MCD Commissioner pulls up engineers over delayed CAQM road works, likely to miss deadline · theprint.in

The Municipal Corporation of Delhi is repairing many roads before the city’s high-pollution months.

Officials checked the projects and said the work was moving too slowly.

About 689 kilometres of roads are finished.

Another 193 kilometres are being worked on.

Some planned projects have not yet been awarded to contractors.

The city also needs Rs 553 crore more for 531 projects.

Engineers must check the work every day and fix problems quickly.

Concrete roads are supposed to finish by October 31, while bituminous roads are due by November 15.

Key facts

Planned road works
1,300 kilometres across 3,110 works initially listed in the action plan.
Completed roads
689 kilometres completed.
Ongoing roads
193 kilometres under actual work; 565 kilometres were described as in progress or partially completed.
Pending awards
82 kilometres of work had yet to be awarded.
Funding gap
Rs 553 crore additionally required for 531 works covering 262 kilometres.
Concrete-road deadline
October 31.
Bituminous-road deadline
November 15.