Indira Gandhi Airport’s Third Runway To Begin Operations September 20

Indira Gandhi Airport’s Third Runway To Begin Operations September 20
Third Runway At Indira Gandhi International Airport To Begin Operations From Sept. 20: DIAL · deccanchronicle.com

Delhi’s main airport is getting a third usable runway.

Delhi International Airport Limited said it will start operating on September 20.

The runway was repaired and upgraded during a project that began in February 2026.

Workers resurfaced the runway and strengthened its pavement.

They also built a new taxiway to help planes leave the runway faster.

New lighting and other electrical and civil improvements were added.

Officials said the work passed inspections and received the required approvals.

The upgrades are expected to help planes move more smoothly and safely, including during different weather conditions.

Key facts

Operator
Delhi International Airport Limited
Airport
Indira Gandhi International Airport
Operations begin
September 20
Project start
February 2026
New taxiway
Rapid Exit Taxiway RET Z1
Runway work
Resurfacing, pavement strengthening, and permanent threshold displacement of runway 29L
Approvals
Required inspections, validations, and regulatory clearances have been completed

Quotes

Delhi International Airport Limited (DIAL)

Airport operator responsible for managing Indira Gandhi International Airport

“The rehabilitation project, which commenced in February 2026, involved extensive strengthening and upgrade works aimed at enhancing operational safety, efficiency, resilience, and long-term capacity at one of India's busiest aviation gateways. The upgraded runway is now ready for operational use after undergoing all required inspections, validations, and regulatory clearances.”