Pologround Substation Marks Six Decades Powering Indore’s Transformation

Pologround Substation Marks Six Decades Powering Indore’s Transformation
Indore’s 60-Year-Old Powerhouse: How Pologround Substation Fuelled City’s Transformation · freepressjournal.in

The Pologround Substation has supplied electricity to Indore for 60 years.

It began working in 1966, when the city was famous for its textile mills.

The substation helped power factories, homes and other businesses.

Indore later grew into a centre for manufacturing, medicines, information technology, education and healthcare.

At first, it had only one transformer and two feeders.

Today, it has three transformers and 16 feeders.

Engineers have added computers, digital meters and monitoring systems to improve safety and reliability.

The substation continues to help Indore grow and prepare for future energy needs.

Key facts

Commissioned
August 30, 1966
Original configuration
One 10 MVA transformer and two outgoing 33 kV feeders
Current transformer capacity
Three transformers with a combined capacity of 176 MVA
Current feeders
16 operational 33 kV feeders
Original transformer
A nearly 25-tonne, 10 MVA transformer manufactured by Hitachi, Japan
Modern systems
Numerical relays, digital metering, advanced controls, communication upgrades and SCADA-based monitoring
Infrastructure upgrade
33 kV overhead networks within the premises were converted into underground cables