Mumbai Monorail Reopening Faces Three-to-Four-Month Safety Delay

Mumbai Monorail Reopening Faces Three-to-Four-Month Safety Delay
Mumbai Monorail Reopening: Safety Net Installation May Delay Services By 3-4 Months · freepressjournal.in

Mumbai’s monorail has been closed since September 2025 because trains had repeated technical problems.

Officials later upgraded the trains, signalling system, and tracks.

The upgraded system was declared safe for passengers in June.

However, officials are now considering adding nets below the elevated tracks.

The nets could stop loose pieces from falling onto roads and people.

Installing them may take another three or four months.

Some reports suggest trains could return around Diwali, while others say December is more likely.

If service returns earlier, it may initially operate only between Chembur and Wadala Depot.

Officials are still deciding whether nets are needed along the entire route or only in vulnerable areas.

Key facts

Service suspension
Operations stopped on September 20, 2025.
Safety approval
The revamped system was approved for passenger services on June 3.
Potential delay
Safety-net installation may require approximately three to four months.
Possible reopening
Reports mention early November around Diwali or December.
Full corridor length
The Chembur-Sant Gadge Maharaj Chowk corridor is 19.54 kilometres long.
Possible first phase
The Chembur-Wadala Depot section covers 8.93 kilometres.
Earlier incident
A load wheel fell onto Ramakrishna Chemburkar Road in July 2016; no casualties were reported.

Quotes

Two people familiar with the Mumbai Monorail

Sources familiar with the Mumbai Monorail, quoted by Hindustan Times

“Between the guideway beams (tracks) and the road, there is no protection to hold any loose material that might fall onto the road.”
freepressjournal.in
“If the route has to be reopened around Diwali, it will be partial, from Chembur to Wadala Depot.”
freepressjournal.in