CAG flags unrealistic rates, cost overestimation by CPWD

CAG flags unrealistic rates, cost overestimation by CPWD
CAG highlights unrealistic rates, cost overestimation by CPWD · indianexpress.com

The government has a special team called the CAG that checks how tax money is spent.

This team looked at another government group called CPWD.

CPWD is in charge of building and repairing government buildings.

It makes a big list of prices for those jobs, called the Schedule of Rates.

The CAG found that the prices on this list were too high.

It says the real-world prices are usually much lower.

In fact, 93 out of every 100 projects got bids that were cheaper than the official estimate.

The CAG says CPWD did not check the markets before making the list in 2021.

This means the government may have been guessing prices instead of using real ones.

The report was shared with Parliament so leaders could see the problem.

Key facts

Auditor
Comptroller and Auditor General of India (CAG)
Audited agency
Central Public Works Department (CPWD)
Report
CAG report on Union Government's Economic and Service Ministries
Works analyzed
5,011 works (January 2022 - January 2023)
Works awarded below estimate
4,666 works (93%)
Flagged schedule
Delhi Schedule of Rates 2021
Key finding
No market survey conducted before the 2021 revision

Quotes

CAG report

Verbatim excerpt from the Comptroller and Auditor General of India report

“The methodology adopted by CPWD for collection of base rates was not realistic.”