Pune Water Tenders Face Scrutiny Over Eligibility Allegations

Pune Water Tenders Face Scrutiny Over Eligibility Allegations
Pune: PMC Water Tenders Under Scanner Over Bidder Scrutiny Allegations - VIDEO · freepressjournal.in

The Pune civic body issued tenders for repairing and maintaining water pipelines.

A political organization representative says the rules may not have been applied consistently.

He questioned why one contractor was accepted in one tender but rejected in another.

He also asked why two different names appeared for another bidder.

He questioned how that bidder’s financial capacity was calculated.

Another contractor was rejected for not listing ongoing work liabilities.

The representative wants officials to investigate the documents and decisions.

He also wants the tenders paused while the inquiry happens.

The Pune Municipal Corporation had not given its response when the report was published.

Key facts

Authority
Pune Municipal Corporation Water Supply Department
Tender numbers
PMC/WATER_SUPPLY/2026/185 and 186
Tender 185 scope
Daily maintenance and repair of water pipelines in Manjari, Shewalwadi and adjoining areas
Estimated value
Approximately ₹84.14 lakh
Main eligibility question
BSK CONSTRUCTION was reportedly eligible in Tender 185 but disqualified in Tender 186 for insufficient work experience
Bidder-name discrepancy
ICON ENTERPRISES appears in the tender summary, while ICON ELECTRONICS appears in meeting minutes
Requested action
Inquiry, suspension of proceedings and possible cancellation and re-tendering if irregularities are established

Quotes

Amol Ramnath Pardeshi

Nationalist Youth Congress Pune City office-bearer who raised allegations about the PMC tenders

“If the contractor did not have the required experience, on what basis was BSK CONSTRUCTION declared eligible in Tender 185? And if the experience was available, why was it disqualified in Tender 186?”