Barapullah Phase-III Opens to Traffic, Faces Three-Kilometre Jam

Barapullah Phase-III Opens to Traffic, Faces Three-Kilometre Jam
Delhi: Commuters report 3-km-long traffic jam on Barapullah Phase-III stretch day after opening · theprint.in

A new elevated road in Delhi opened to help people travel faster between east and south Delhi.

But on its first full day, many cars became stuck in a long traffic jam.

The line of vehicles from Mayur Vihar Phase-1 toward Sarai Kale Khan was nearly 3 km long.

Some drivers said they spent 40 to 55 minutes reaching parts of the new road.

The Delhi Traffic Police said it had noticed the problem and would send more officers to busy joining and leaving points.

Officials are studying how traffic is moving and plan to make changes.

The road connects Mayur Vihar Phase-1 with Sarai Kale Khan and continues toward AIIMS.

The other direction, from AIIMS toward Mayur Vihar, was expected to open by Thursday afternoon.

Key facts

Reported tailback
Nearly 3 km from Mayur Vihar Phase-1 toward Sarai Kale Khan
Reported travel delays
About 40 minutes for one commuter and 55 minutes to reach the first intersection for another
Corridor route
Mayur Vihar Phase-1 on Noida Link Road to Sarai Kale Khan on Ring Road
Signal-free stretch
About 9 km to the AIIMS roundabout when joined with the existing Barapullah network
Project cost
Rs 1,635 crore
Project timeline
Approved in 2014; construction began in 2015 and was initially scheduled for completion in 2017
Planned traffic response
More regulation and stronger deployment at critical merging and exit points

Quotes

A traffic officer

Delhi traffic official responding to reports of congestion on the new corridor

“The congestion reported on the newly-opened Barapullah Phase-III corridor, including the tailback from the Mayur Vihar side, has been noted on priority. Traffic officers have been directed to intensify regulation and strengthen deployment at critical merging and exit points.”
theprint.in