Barapullah Phase 3 Set to Open September 29

Barapullah Phase 3 Set to Open September 29
Barapullah phase 3 corridor linking Mayur Vihar, AIIMS to open by end of September · theprint.in

Barapullah Phase 3 is a new elevated road corridor in Delhi.

It will connect Mayur Vihar with the AIIMS area.

Officials expect it to open by the end of September, with an inauguration planned for September 29.

The road will join the existing Barapullah flyover near Sarai Kale Khan.

This should give drivers a route with fewer traffic signals.

The project will also have a special path for bicycles.

It includes facilities designed to make walking easier and a bridge over the Yamuna.

The project took longer and cost more than originally planned.

Key facts

Expected inauguration
September 29
Expected opening
By the end of September
Corridor length
Approximately 9 kilometres
Route
Mayur Vihar Phase 1 to AIIMS
Project cost
Approximately ₹1,635 crore
Project approval
2014
Construction start
2015
Original completion target
2017

Quotes

Parvesh Sahib Singh

Delhi Public Works Department minister

“The project is also set to become a landmark in urban infrastructure development. For the first time in India, a flyover corridor has been designed with a dedicated cycle track, promoting greener and more sustainable mobility for Delhiites.”