3 weeks ago

Maharashtra Introduces Performance Rating System for Infrastructure Contractors

Maharashtra Introduces Performance Rating System for Infrastructure Contractors
Maharashtra Introduces Performance Rating System For Contractors Handling ₹500-Crore-Plus Infrastructure Projects · freepressjournal.in

The government of Maharashtra has made a new rule for big building projects.

The rule applies to projects that cost ₹500 crore or more, like roads, metros, and other large works.

Companies that build these projects will now be checked and given points.

They can earn up to 100 points in total.

Doing quality work is worth 60 points, finishing on time is worth 30 points, and keeping the work in good shape afterwards is worth 10 points.

Companies with more than 80 points are called 'Green' and get normal treatment in tenders.

Companies with 60 to 80 points are called 'Yellow' and must pay extra security money.

Companies with less than 60 points are called 'Red' and cannot take part in new projects at all.

Companies will also need a special Performance Certificate to prove their past work is good.

The rule is meant to reward good builders and stop poorly performing ones from getting government contracts.

Key facts

Framework
Contractor Performance Assessment and Rating (PAR) Framework
Applicability
Upcoming tenders worth ₹500 crore or more
Issuing body
Public Works Department, Maharashtra government
Marking scheme
Quality of work 60, timely completion 30, maintenance/overall performance 10 (total 100)
Contractor categories
Green (above 80), Yellow (60-80), Red (below 60)
Yellow category condition
Performance security at 1.10 times the specified rate
Red category condition
Disqualified from the tender process
Performance Certificate validity
12 months, issued by an officer of Chief Engineer rank or above

Sources

Related news