PWD Plans Repairs for Three Major South Delhi Flyovers
Delhi’s Public Works Department wants to repair parts of three important flyovers in South Delhi.
They are the Nehru Nagar flyover, the AIIMS flyover and a loop linked to Barapullah Phase 1.
These roads connect important parts of South Delhi with places such as DND and Sarai Kale Khan.
The repairs are intended to make the flyovers safer and help them last longer.
Workers will replace expansion joints and perform other routine maintenance.
The project is expected to cost Rs 1.3 crore.
It should take about four months after the work is awarded.
Barriers will be added to stop heavy vehicles from using a restricted stretch.
Officials will coordinate with traffic police before construction begins.
The Public Works Department plans repairs on the Nehru Nagar, AIIMS and Barapullah Phase 1 flyovers.
The project is estimated to cost Rs 1.3 crore and should take four months after the work is awarded.
Workers will replace single-strip seal expansion joints and carry out other routine repairs.
Height barriers will be installed at Nehru Nagar to restrict trucks and buses from using the Barapullah flyover link.
Construction will begin after consultations with traffic police because the repairs may affect traffic movement.
- Who
- The Public Works Department will oversee the repairs, in consultation with traffic police.
- What
- Repair and maintenance work is planned for stretches of the Nehru Nagar, AIIMS and Barapullah Phase 1 flyovers.
- Where
- South Delhi, including the Outer Ring Road and routes linking Mathura Road, Ashram Chowk, AIIMS, South Extension and Lajpat Nagar.
- When
- The plan was reported on August 26; work is expected to take four months after it is awarded.
- Why
- To extend the flyovers’ lifespan, address possible cracks or structural damage and improve road-user safety.
Key facts
- Project
- Repair and maintenance of three major South Delhi flyover stretches
- Flyovers involved
- Nehru Nagar, AIIMS and Barapullah Phase 1
- Estimated cost
- Rs 1.3 crore
- Expected duration
- Four months after the work is awarded
- Main repair
- Replacement of single-strip seal expansion joints and other routine repairs
- Traffic measure
- Height barriers will be installed at the start of the Nehru Nagar flyover
- Vehicle restriction
- Trucks and buses are not allowed on the Barapullah flyover
Quotes
A PWD official
An official from Delhi’s Public Works Department
“The main objective of the repair and rehabilitation of the flyovers is to increase their lifespan and ensure the safety of road users passing over or under them. Over time, infrastructure exposed to high vehicular loads can develop cracks or structural damage.”
thehansindia.com
theprint.in
“The work involves replacement of single-strip seal expansion joints, including dismantling and removal of existing joints, along with other routine repairs to ensure that the flyovers comply with safety norms.”