Special measures announced to resolve Udandapur reservoir rehabilitation issues

Special measures announced to resolve Udandapur reservoir rehabilitation issues
Special measures in place to resolve Udandapur R&R issues · thehansindia.com

Officials met to discuss families moved because of the Udandapur Reservoir.

They checked whether these families had received their compensation and rehabilitation support.

Officials said nearly all land acquisition awards were complete.

Most payments for land, houses and house sites had been deposited into beneficiaries’ accounts.

The remaining cases will be examined one by one.

Village leaders must hold meetings so people can receive plots and build houses.

Complaints must receive clear written answers.

Officials and elected representatives will meet every 15 days to solve pending problems.

Key facts

Project
Udandapur Reservoir
Awards completed
Nearly 99 per cent of land acquisition awards
Compensation
Amounts for land acquisition, house packages and house sites were deposited into beneficiaries’ accounts
Remaining cases
The final one per cent will be examined individually
Plot allotment
Sarpanches were directed to hold gram sabhas and expedite allotments in R&R layouts
Review schedule
The MLA, public representatives and officials will meet every 15 days
Infrastructure concerns
Burial grounds or crematoriums, function halls and roads in rehabilitation areas

Sources

Related news