Nashik Kumbh Projects Face Delays Ahead of March 2027 Deadline

Nashik Kumbh Projects Face Delays Ahead of March 2027 Deadline
Nashik: 70% Work Pending On 35 Major Kumbh Road, Bridge Projects; March 2027 Deadline Nears · freepressjournal.in

Nashik is building roads and bridges for the 2027 Simhastha Kumbh Mela.

There are 35 major projects in total.

These include 28 road projects and seven bridge projects.

Together, they cover about 150 kilometres and cost around ₹1,400 crore.

Most of the work is only about 30% finished.

This means roughly 70% still needs to be completed.

Officials say some approvals arrived late and in stages.

Authorities now need to speed up the work while maintaining construction quality before March 2027.

Key facts

Total projects
35 major projects: 28 roads and seven bridges
Project coverage
Approximately 150 kilometres
Estimated cost
Around ₹1,400 crore
Overall progress
Most projects are approximately 30% complete
Pending work
Approximately 70% remains
Best-reported progress
The Nasardi River bridge at Milind Nagar is about 45% complete
Deadline
March 2027