Corpus Christi’s desalination plan leaves city facing a water crisis
Corpus Christi, a city in South Texas, is facing a severe water shortage after a long-promised seawater desalination plant failed to materialize.
In 2018, city leaders approved a plan for major industrial water users to help pay for the plant, which was meant to supply millions of gallons of freshwater each day.
The companies originally agreed to cover more of the cost, but now contribute only a fraction of the expected total, leaving residents to pay the rest.
The city has spent at least $50 million, but political turmoil, the pandemic and rising costs have stalled the project.
During the drought, the city did not press refineries and chemical plants to cut their water use, even as reservoirs nearly dried up.
Those industries use more water than the 500,000 residents of the seven-county Coastal Bend region combined.
The dispute has raised questions about who should bear responsibility for the crisis and the costs of new water supplies.
A public referendum on industrial water fees is planned for November.
A plan to build a seawater desalination plant has left Corpus Christi facing a water-supply crisis, according to an Inside Climate News report.
The city has spent at least $50 million on the plant, which has not been built.
Companies that originally agreed to fund the project now contribute only a fraction of its expected cost, leaving residents to pay the rest.
The city has not pressed industrial users to reduce water use, even as drought nearly emptied the region’s main reservoirs.
An activist blamed industrial water use for the crisis, while a trade group executive said city leaders failed to deliver the promised water supply.
- Who
- Corpus Christi and the industrial companies that use its water, including OxyChem, Valero and Citgo.
- What
- A planned seawater desalination plant has not materialized, while the city faces a water-supply crisis.
- When
- The plan was approved in 2018. The region’s main reservoirs were nearly dry by spring 2026.
- Where
- Corpus Christi and the seven-county Coastal Bend region in South Texas.
- Why
- The report cites drought, the unfinished desalination plant and high industrial water use. The parties disagree about responsibility for the crisis.
Isabel Araiza and community campaigners
Industrial companies and their trade group
Responsibility for the crisis
Isabel Araiza and community campaigners
Araiza said industrial water use caused the crisis.
Industrial companies and their trade group
Bob Paulison said the companies were not responsible and that city leaders failed to build the promised water supply.
Water use during drought
Isabel Araiza and community campaigners
Araiza opposed the desalination project, and the city did not pressure companies to cut water use during drought.
Industrial companies and their trade group
The companies had agreed to fund a drought-proof supply, according to Paulison.
Consultant Frank Brogan presented the desalination plan to Corpus Christi City Council.
City leaders unanimously approved the plan.
The region’s main reservoirs had almost dried up entirely.
Isabel Araiza led a petition campaign that collected almost 13,000 verified signatures for a November referendum on industrial water fees.
- City spending
- At least $50 million on the planned desalination plant
- Original plan
- Companies would pay the city to build a seawater desalination plant
- Industrial water use
- More than the combined use of all 500,000 residents of the seven-county Coastal Bend region
- Petition signatures
- Almost 13,000 verified signatures
- Referendum
- November vote on industrial water fees
What people are saying
The reason we were in the water crisis was because of their water usage
you kept dragging