Worli Flyover and Subway Target January 2027 Completion

Worli Flyover and Subway Target January 2027 Completion
Mumbai Infra Update: Worli Flyover, Subway Targeted By January 2027 To Cut Travel Time By Upto 15 Minutes · freepressjournal.in

The Nehru Science Centre and Nehru Planetarium are close to each other in Worli.

Drivers currently have to take a longer route through the busy Worli Naka.

The Brihanmumbai Municipal Corporation is building a flyover and subway to create a more direct route.

The new link will connect E Moses Road and Annie Besant Road.

It is being built over the Nehru Science Centre drain.

The project is expected to be completed by January 31, 2027.

Drivers could save as much as 15 minutes on this trip.

Officials said much of the foundation and structural work has already been completed.

They are also preparing a traffic plan with the traffic police for the remaining work.

Key facts

Completion deadline
January 31, 2027
Project cost
Rs 285.61 crore
Flyover length
571 metres
Roads linked
E Moses Road and Annie Besant Road
Current detour
Nearly 2 kilometres through Worli Naka
Potential time saving
Up to 15 minutes
Construction progress
Main piling is complete; 17 of 18 girder spans have been fabricated and nine have been erected