Andheri Flyover Repairs Rise Above ₹130 Crore, Delayed To 2026

Andheri Flyover Repairs Rise Above ₹130 Crore, Delayed To 2026
Mumbai: Andheri Flyover Repair Cost Jumps Over 40 Per Cent To ₹130.36 Crore; Completion Pushed To November 2026 · freepressjournal.in

The Andheri flyover in Mumbai needs major repairs.

The repairs were first expected to cost ₹92.67 crore.

The estimated total has now risen to ₹130.36 crore, including taxes and other charges.

The work is also expected to finish in November 2026.

Engineers found that more parts, including beams and columns, needed strengthening.

They also detected vibrations while traffic was still using the flyover.

BMC must pay for the extra work after the state directed it to follow the engineers’ recommendations.

The flyover became a major concern after part of it fell onto a car in July 2024.

Key facts

Original estimate
₹92.67 crore
Latest estimated cost
₹130.36 crore, including taxes
Proposed completion
November 2026
Contractor
M/s Freyssinet Prestressed Concrete Co. Ltd.
Revised contract value
₹105.53 crore before the listed additional charges
Additional strengthening estimate
₹10.87 crore for columns and beams
Structural audit
VJTI recommended strengthening after a 2023 audit
Collapse incident
A portion of the flyover collapsed onto a car on July 4, 2024