Mumbai Metro Line 9 Phase 2 Integration Trials Begin
Mumbai Metro is testing a new part of Line 9.
The new section has three additional stations.
Workers must connect it safely to Metro Lines 2A, 7 and Line 9 Phase 1.
They are testing the signalling system, which helps trains move safely.
These tests are taking place before the new section can open to passengers.
Testing began on September 15, 2026, and is planned through September 25.
Because the work happens in the morning, some Metro services will start later than usual.
Lines 2A, 7 and Line 9 Phase 1 will start carrying passengers at 6:30 a.m.
during this period.
Signalling and integration trials for Metro Line 9 Phase 2 began on September 15, 2026.
The trials are connecting three additional stations to the operational Metro network.
A special morning non-revenue block will run from September 15 through September 25.
Lines 2A, 7 and Line 9 Phase 1 will begin passenger services at 6:30 a.m. during the block.
Testing includes signalling software migration, validation and speed trials through the Operations Control Centre at Charkop Depot.
- Who
- The Maha Mumbai Metro Operation Corporation Limited and its technical teams are conducting the trials.
- What
- Signalling, software migration, integration and speed trials for Metro Line 9 Phase 2 have begun.
- Where
- The integration is being conducted through the Operations Control Centre at Charkop Depot and involves Lines 2A, 7 and Line 9 Phase 1.
- When
- The trials and special morning block are scheduled from September 15 through September 25, 2026.
- Why
- The work is needed to safely integrate the three additional stations with the operational Metro network before commissioning.
Key facts
- Project
- Metro Line 9 Phase 2
- Trial start
- September 15, 2026
- Special block
- September 15–25, 2026
- Affected services
- Metro Lines 2A, 7 and Line 9 Phase 1
- Temporary start time
- 6:30 a.m.
- Testing location
- Operations Control Centre at Charkop Depot
- Next milestone
- Completion of integration and speed trials before the next commissioning stage