MRVC Advances Bhivpuri and Vangaon EMU Carshed Projects

MRVC Advances Bhivpuri and Vangaon EMU Carshed Projects
MRVC Speeds Up Work On New EMU Carsheds At Bhivpuri And Vangaon · freepressjournal.in

The Mumbai Railway Vikas Corporation is building two new places to repair and maintain suburban trains.

These places will be at Bhivpuri and Vangaon.

At Bhivpuri, all the required land has been acquired.

Much of the soil and ground preparation work there is already finished.

At Vangaon, some private land has been acquired, while forest land still needs additional approval.

The project received its first forest clearance in February 2026.

Both facilities are part of a larger plan to support more and newer trains.

The new carsheds should help Mumbai’s suburban railway maintain its trains more effectively.

Key facts

Bhivpuri site
45.24 hectares, comprising 42.28 hectares of private land and 2.96 hectares of government land.
Bhivpuri land status
All required land has been acquired.
Bhivpuri earthwork
About 7.16 lakh cubic metres has been completed.
Vangaon site
Approximately 43.68 hectares is required.
Vangaon private land
The entire 3.64 hectares of private land has been acquired, with compensation deposited for disbursement.
Forest clearance
Vangaon received Stage-I in-principle clearance in February 2026; Stage-II clearance is under process.
Programme
The carsheds are being developed under MUTP-IIIA alongside expansion of existing EMU maintenance facilities.