India’s Semiconductor Push Exposes a Missing Water Budget

India’s Semiconductor Push Exposes a Missing Water Budget
Counting the Water · thestatesman.com

A large chip factory is being built in Dholera, where the underground water is salty and cannot supply the factory.

The factory plans to bring water from the Narmada River through canals.

It will use thousands of kilolitres of water every day, although much of the water will be recycled.

Supporters say chip factories recycle water and use surface water instead of taking more from underground.

Critics say the river and canals are already needed by farms and towns.

Other chip factories and data centres may also need water in the same region.

Each project is currently checked separately, so officials may not see the total demand.

The article recommends adding up all water uses within each river basin.

This would help decide whether a new factory should be approved, moved, desalinate water or be refused.

Key facts

Dholera fab operator
Tata Electronics
Daily water requirement
About 17,549 kilolitres, including approximately 6,571 kilolitres of fresh water
Planned water source
The Narmada River, transported through a canal
Target production
About 50,000 wafers per month at mature nodes from 28 to 110 nanometres
Second India Semiconductor Mission
Approved by the Union Cabinet on 15 July 2026 with an outlay of Rs 1.27 lakh crore
CG Semi plant
A Rs 7,600-crore assembly-and-test plant inaugurated at Sanand on 4 July 2026
Micron water assurance
More than 20 million litres per day of Narmada water, scalable to 90 million litres per day
Proposed policy
A public basin-level annual withdrawable water envelope, with industrial approvals debited against it