Indore Sets October Deadlines for Key Master Plan Road Stretches

Indore Sets October Deadlines for Key Master Plan Road Stretches
Master Plan Roads: Key Stretches Set For October Completion · freepressjournal.in

Indore is building several roads as part of its Master Plan.

The city’s municipal commissioner met with the agencies doing the work.

He told them to add workers and equipment where needed so projects can finish on time.

Some road sections have deadlines in October.

Other work, including culvert construction and a road near Gutkeshwar Temple, also needs to move faster.

Officials must finish fencing near City Forest before starting the road there.

Construction sites must have safety measures such as barriers and signs.

The commissioner also asked agencies and city departments to work together to solve delays.

Key facts

Review meeting
Held at the Smart City office
Packages reviewed
Packages 1, 2 and 4
Package 1 deadline
Victory One was directed to complete the Neminath via Jinsi to Laxmibai statue two-lane road by October 30.
Package 2 deadline
SKS Construction was directed to complete the Sanwer Road petrol pump to Shivshakti Nagar road by October 25.
Package 4 deadlines
The Musakhedi to Shri Sanwaria Dham Temple service road is due October 30; the Gutkeshwar Road four-lane work is due October 25.
Other work
Fencing in the City Forest area must be completed before road construction begins on the Hotel Pride to City Forest project.
Site safety
Agencies were directed to provide barricading, signage and other necessary safety measures.