Indore Sets October Deadlines for Key Master Plan Road Stretches
Indore is building several roads as part of its Master Plan.
The city’s municipal commissioner met with the agencies doing the work.
He told them to add workers and equipment where needed so projects can finish on time.
Some road sections have deadlines in October.
Other work, including culvert construction and a road near Gutkeshwar Temple, also needs to move faster.
Officials must finish fencing near City Forest before starting the road there.
Construction sites must have safety measures such as barriers and signs.
The commissioner also asked agencies and city departments to work together to solve delays.
Municipal Commissioner Kshitij Singhal directed construction agencies to speed up work on Master Plan road projects in Packages 1, 2 and 4.
Victory One was told to finish the Neminath–Jinsi–Laxmibai statue road by October 30.
SKS Construction was given an October 25 deadline for the Sanwer Road petrol pump–Shivshakti Nagar road.
PD Agrawal Infrastructure Ltd was directed to complete the Musakhedi–Shri Sanwaria Dham Temple service road by October 30 and the Gutkeshwar Road work by October 25.
Agencies were ordered to improve coordination, provide proper barricades and signs, and follow safety standards at construction sites.
- Who
- Municipal Commissioner Kshitij Singhal and agencies working on Indore’s Master Plan road projects.
- What
- Singhal directed agencies to accelerate road construction, meet specified deadlines, coordinate to resolve obstacles, and enforce construction-site safety.
- Where
- Indore, Madhya Pradesh, including road projects in Packages 1, 2 and 4.
- When
- The review meeting was held on Thursday; several project deadlines are October 25 and October 30, with one action plan covering the next three months.
- Why
- To complete the road works within prescribed timelines and prevent inconvenience and accidents around construction zones.
Key facts
- Review meeting
- Held at the Smart City office
- Packages reviewed
- Packages 1, 2 and 4
- Package 1 deadline
- Victory One was directed to complete the Neminath via Jinsi to Laxmibai statue two-lane road by October 30.
- Package 2 deadline
- SKS Construction was directed to complete the Sanwer Road petrol pump to Shivshakti Nagar road by October 25.
- Package 4 deadlines
- The Musakhedi to Shri Sanwaria Dham Temple service road is due October 30; the Gutkeshwar Road four-lane work is due October 25.
- Other work
- Fencing in the City Forest area must be completed before road construction begins on the Hotel Pride to City Forest project.
- Site safety
- Agencies were directed to provide barricading, signage and other necessary safety measures.