Chakan Industrial Infrastructure Projects Accelerate to Ease Traffic Congestion

Chakan Industrial Infrastructure Projects Accelerate to Ease Traffic Congestion
Chakan MIDC Infrastructure Works Gain Pace; Focus On Easing Traffic Congestion, Says Pune District Collector Jitendra Dudi · freepressjournal.in

Chakan is a busy industrial area near Pune where many vehicles use the roads.

Officials met to check whether improvement projects were moving forward.

Some roads have already been completed, while others are still being built.

The projects include wider roads, footpaths, dividers and better road shoulders.

A parking facility is now operating to help reduce roadside parking.

More traffic staff, a crane and wheel clamps will help manage blocked or wrongly parked vehicles.

Officials also want permanent drains to prevent waterlogging during the monsoon.

Work has started on a transformer to improve electricity supply.

They also plan regular road maintenance and landscaping.

Key facts

Completed road work
A 5.5-kilometre cement-concrete stretch on the 75-metre-wide main road in Phase II is complete.
Six-lane road
The 4.03-kilometre Phase IV road, including footpath repairs, dividers and beautification, is 80% complete.
Roads under review
The review covered 25 kilometres of MIDC roads, 12.8 kilometres of national highways, 22 kilometres under the Maharashtra State Infrastructure Development Corporation and 17.5 kilometres under PMRDA.
Traffic measures
Approval was secured for 45 MSF personnel, while MIDC approved a crane and 50 wheel clamps for traffic police.
Parking
A designated parking facility has become operational, and road-shoulder work is underway.
Power supply
Transformer work is about 25% complete, with officials saying the facility will provide more power than MIDC currently expects.
Drainage
Officials were instructed to create a permanent drainage system at locations prone to waterlogging.