1 week ago

Sunsure Energy’s Uttar Pradesh Renewable Portfolio Surpasses 500 MWp

Sunsure Energy’s Uttar Pradesh Renewable Portfolio Surpasses 500 MWp
Sunsure Energy’s renewables portfolio in UP surpasses 500 MWp-mark · thehindubusinessline.com

Sunsure Energy builds and operates renewable-energy projects such as solar plants and batteries.

Its renewable-energy portfolio in Uttar Pradesh is now about 506.5 megawatts.

One important project is a 105-megawatt solar plant in Kabrai.

The plant began operating in only four months.

It is the first plant to send clean electricity through a new transmission corridor in the state.

The corridor is being built to carry solar power from the Bundelkhand region.

Sunsure is also developing more solar capacity and a large battery project in Uttar Pradesh.

The company wants to have 10,000 megawatts of operating capacity by 2030.

Key facts

Uttar Pradesh portfolio
Approximately 506.5 MW
Kabrai project
105 MWp solar project commissioned in four months
Commissioned capacity
292.5 MWp across Erach, Kabrai and Charkhari
Hamirpur project
75 MWp solar project under development
Battery project
500 MWh grid-scale battery project under development in Jhansi
Green Energy Corridor-II
A nearly ₹5,400 crore Uttar Pradesh transmission investment involving 21 substations and infrastructure to evacuate nearly 4,000 MW of solar power
2030 target
10,000 MW of operational capacity

Quotes

Kartikeya Narain Sharma

Co-Founder and Chief Business Officer at Sunsure Energy

“This portfolio includes our commissioned plants in 2026-Erach, Kabrai, and Charkhari with a cumulative capacity of 292.5 MWp and is spread across 1,000 acres in Jhansi and Mahoba districts. Another 75 MWp solar project is under development in Hamirpur, along with a 500 MWh grid-scale battery energy storage project in Jhansi that will supply peak power solutions to Uttar Pradesh Power Corporation (UPPCL). It is among the largest commercial battery storage builds in the country.”
thehindubusinessline.com
“We recently commissioned two solar projects at Charkhari and Kabrai in Mahoba district. The 105 MWp Kabrai project was commissioned in 4 months and is the first solar project to evacuate green power under the Uttar Pradesh Green Energy Corridor-II (GEC-II) project.”
thehindubusinessline.com