22 hrs ago
UP Begins Month-Long Power Maintenance Drive Before Major Festivals
Uttar Pradesh is preparing its electricity system for the upcoming festivals.
The power department will run a special maintenance campaign for one month.
It will take place from September 15 to October 14, 2026.
Workers will inspect substations, transformers, wires, and other equipment.
They will repair broken parts and fix problems that cause repeated outages.
Tree branches near power lines will also be cut back to help prevent disruptions during storms.
Officials will try to avoid power cuts during festival days.
Senior officers will conduct surprise inspections to check whether the work was really completed.
Uttar Pradesh Power Corporation will observe Maintenance Month from September 15 to October 14, 2026.
The drive aims to improve electricity reliability before Navratri, Dussehra, and Deepawali.
Substations, power transformers, distribution transformers, feeders, lines, and other equipment will be inspected and repaired.
Officials will replace damaged equipment, fix loose connections, remove makeshift wiring, and prune tree branches near power lines.
Area plans are due by September 10, while surprise inspections and work verification will take place later in October.
- Who
- The Uttar Pradesh Power Corporation, its distribution corporations, and state energy officials, under directions from Dr. Ashish Kumar Goyal.
- What
- A month-long maintenance campaign to inspect, repair, and strengthen Uttar Pradesh’s electricity distribution network.
- Where
- Across Uttar Pradesh, including its substations, feeders, transformers, and distribution lines.
- When
- Maintenance Month will run from September 15 to October 14, 2026; work verification is scheduled for October 21–27.
- Why
- To address faults linked to summer and monsoon conditions and improve reliable electricity supply during Navratri, Dussehra, and Deepawali.
Key facts
- Campaign
- Maintenance Month
- Campaign period
- September 15 to October 14, 2026
- Planning deadline
- Area-wise action plans must be prepared by September 10.
- Equipment covered
- 33/11 kV substations, power transformers, distribution transformers, feeders, and electricity lines.
- Planned work
- Inspections, cleaning, repairs, replacement of worn-out wires and damaged equipment, and tree-branch pruning.
- Verification period
- October 21 to October 27 at corporation and headquarters levels.
- Operational priority
- Avoid shutdowns during festival days and minimize inconvenience when shutdowns are necessary.