Mumbai Metro Line 7A Faces Airport Height Clearance Hurdle

Mumbai Metro Line 7A Faces Airport Height Clearance Hurdle
Mumbai Metro Line 7A Faces Height Clearance Hurdle As MMRDA Holds SYSTRA Consultant Responsible For OHE Design Lapse · freepressjournal.in

Mumbai is building a metro line to connect Andheri East with the airport.

The trains will use overhead electrical equipment called OHE.

MMRDA says the project consultant did not properly include the extra height needed for this equipment.

The metro must also stay within height limits set because it is near an airport.

MMRDA is waiting for a final technical report from the Airports Authority of India.

After receiving it, MMRDA will decide whether changes are needed.

The consultant, SYSTRA, has previously accused some MMRDA officials of asking for improper payments and causing project delays.

SYSTRA also challenged MMRDA’s decision to end its contract, and the Bombay High Court criticized that decision as unfair and unreasonable.

Key facts

Project
Mumbai Metro Line 7A, an airport-bound extension of Metro Line 7
Length
3.4 kilometres
Consultant
SYSTRA-CEG-SMCIPL consortium
Technical authority
Airports Authority of India
Pending action
AAI’s final report on permissible height clearances
Underground section
Approximately 1.65 kilometres between Andheri East and the airport
Contract dispute
MMRDA discontinued SYSTRA’s services on January 3, 2025, despite an extension through December 2026

Quotes

Bombay High Court

Bench comprising Chief Justice Alok Aradhe and Justice Arif Doctor

“We find that the action of the MMRDA in discontinuation of the terms of the contract, which was extended up to December 2026, without assigning any reasons, is arbitrary, unfair and unreasonable.”
freepressjournal.in
“The additional height required for the OHE system was not adequately highlighted and factored in by the Consultant at the appropriate stage of design and planning.”
freepressjournal.in